MOX Project Status

MOX Project Status

Over the past several years, despite lower levels of funding, MOX construction continues to progress with a strong nuclear safety and quality record. As of July 2016, progress included 93% of concrete and 96% of rebar installed; 325 glove boxes on contract with 129 installed; 27 of 28 long lead glove boxes tested; 72 of 73 tanks installed; and 22 of 31 Active Gallery modules installed.

Visit our Photo gallery for up to date photos on construction progress and our MOX updates for the latest information!